Progress at Drungewick Lock. The offside (west) chamber wall above the downstream paddle culvert has been taken down to the invert. Since the pictures were taken in November 2003, the wall has been built up two courses of 'stone' and backfilled with concrete.

repairs to drungewick lock repairs to drungewick lock
Dec. 7, 2003. Dec 14, 2003.
repairs to drungewick lock repairs to drungewick lock
Making the concrete blocks. The repairs on or about Dec. 21. 2003
repairs to drungewick lock repairs to drungewick lock
David Southgate braves the weather Eddie Fairman consolidates the concrete in the former void behind the quoin
drungewick lock wall repair
At he end of another January day (Jan 11, 2004) Dusty Miller looking into the abyss left where the sheet piling has been removed The repair completed.
waterfall lock
The winding hole cascade. The start of pointing.
lock lock
Down the lock ladder, four layers of scaffolding boards. Two bays of scaffolding moved and Dusty Miller (in red) with wellies full!
lock lock
Pointing the ladder recess. Down the ladder.
lock lock
Pointing the nearside chamber wall. The cascade takes shape.
lock lock
The repaired sill and stop planks removed. Clearing up in Drungewick pound after the gales.

Pictures: Eric Walker.
Click on thumbnails to enlarge.

BACK Last updated March 2004